Educational Services Facility - Additional Electrical Improvements - Construction Management Services - SALES SURTAX
Meeting Date(s)
Consent w/o Information - 10/11/2022
Consent Type
Without Information
Discussion

The School Board approved the Guaranteed Maximum Price (GMP) submitted by Heard Construction, Inc. at the February 22, 2022 meeting. The project is under construction. 

Educational Technology has requested an owner-directed change order to upgrade the uninterruptible power supply (UPS) that protects the primary data center that houses technology that serves the entire district including school connectivity, internet access, AS400, server applications, etc..  This will provide a more robust electrical foundation for the educational technology functions at the Educational Service Facility.  

At the District's request, Heard Construction, Inc. (Heard) has submitted an owner-directed change order for the UPS and related upgrades in the amount of $146,940.29.  The design was prepared by OCI Associates, Inc. under their continuing contract for mechanical, electrical, plumbing and fire protection engineering services. Administration and permitting costs were previously budgeted.  This project will be funded through 2020 sales surtax and Educational Technology capital. 

Board approval is required for change orders over $50,000 or over 10% of the original contract amount.  The change order template has been used, which does not require legal review.

Recommendation

Approve the owner-directed change order submitted Heard Construction, Inc. for the UPS and related electrical upgrades to support Educational Technology at the Educational Services Facility in the amount of $146,940.29.

Authority for Action
F.S. 1001.42
Involves Expenditure of Funds Directly in the Classroom
No
Source of Funding

Capital Projects
Sales Surtax
Financial Impact
FY Amount Budgeted Fund Cost Center Project Function Object Program
22/23 $146,940.29 Yes 397/372 9860 541300 7400 681/687 000
Legal Counsel Review
No
Contact
Susan Hann, P.E., Assistant Superintendent Facilities Services 633-1000 ext. 11446 David Lindemann, AICP, Director of Planning and Project Management 633-1000 ext. 11463 Chris Ault, ET Projects and Technology Manager 633-1000 ext. 11777
Attachments
ESF Electrical Renewal Change Order No. 1 Attachment.pdf