Previous Item | Next Item |
|
||||||||||||||||||
November 22, 2022 Organization of the Board with Oath of Office & School Board Meeting | ||||||||||||||||||
Title Eau Gallie High School CEP Renovation - Close Out | ||||||||||||||||||
Meeting Date(s) Consent w/o Information - 11/22/2022 |
||||||||||||||||||
Consent Type Without Information | ||||||||||||||||||
Discussion On April 27, 2021, the School Board approved the Guaranteed Maximum Price (GMP) submitted by Canaveral Construction Co., Inc., for the Eau Gallie High School Central Energy Plant project in an amount not to exceed $405,680.77. The work has been completed . The final project cost is $400,235.70 which includes $373,589.24 contracted costs and $26,646.46 in owner direct purchases. The unused balance is $5,445.07. | ||||||||||||||||||
Recommendation Authorize the Superintendent to sign FDOE OEF Form 209 - Certificate of Final Inspection for the project. | ||||||||||||||||||
Authority for Action F.S. 1001.42 | ||||||||||||||||||
Involves Expenditure of Funds Directly in the Classroom No | ||||||||||||||||||
Source of Funding Agenda Item will not Require the Expenditure of Funds |
||||||||||||||||||
Financial Impact
| ||||||||||||||||||
Legal Counsel Review No |
||||||||||||||||||
Contact Susan Hann, P.E., Assistant Superintendent of Facility Services 633-1000 ext. 11446, David Lindemann, AICP, Director Planning & Project Management | ||||||||||||||||||
Attachments OEF-209 version 2012 -Eau Gallie CEP 2021.pdf |
||||||||||||||||||
![]() |