Eau Gallie High School CEP Renovation - Close Out
Meeting Date(s)
Consent w/o Information - 11/22/2022
Consent Type
Without Information
Discussion

On April 27, 2021, the School Board approved the Guaranteed Maximum Price (GMP) submitted by Canaveral Construction Co., Inc., for the Eau Gallie High School Central Energy Plant project in an amount not to exceed $405,680.77.

The work has been completed . The final project cost is $400,235.70 which includes $373,589.24 contracted costs and $26,646.46 in owner direct purchases. The unused balance is $5,445.07.

Recommendation

Authorize the Superintendent to sign FDOE OEF Form 209 - Certificate of Final Inspection for the project.

Authority for Action
F.S. 1001.42
Involves Expenditure of Funds Directly in the Classroom
No
Source of Funding

Agenda Item will not Require the Expenditure of Funds
Financial Impact
FY Amount Budgeted Fund Cost Center Project Function Object Program
                 
Legal Counsel Review
No
Contact
Susan Hann, P.E., Assistant Superintendent of Facility Services 633-1000 ext. 11446, David Lindemann, AICP, Director Planning & Project Management
Attachments
OEF-209 version 2012 -Eau Gallie CEP 2021.pdf
Agenda Plus