November 14, 2023, Organization of the Board with Oath of Office & School Board Meeting
Title
Meadowlane Intermediate & Primary Central Energy Plant Renewal - Close Out
Meeting Date(s)
Consent Type
Discussion

On March 9, 2021, the School Board approved the Guaranteed Maximum Price (GMP) submitted by Welsh Construction, LLC, for the Meadowlane Intermediate & Primary Central Energy Plant Renewal project in an amount not to exceed $582,854.00. 

The work has been completed and audited.  The final project cost is $554,539.22 which includes $340,817.42 contracted costs and $213,721.80 in owner direct purchases.  The unused balance is $28,314.78.

Because the cost of construction is over $300,000 the Florida Department of Education requires the Superintendent to sign the Certificate of Final Inspection (OEF-209) following certification by Engineer/Architect of Record and the Building Official.

Recommendation
Authority for Action
F.S. 1001.42
Involves Expenditure of Funds Directly in the Classroom
No
Source of Funding

Agenda Item will not Require the Expenditure of Funds
Financial Impact