May 25, 2021 School Board Meeting | ||||||||||||||||||
Title District School Security GMP#2 - Close Out | ||||||||||||||||||
Meeting Date(s) |
||||||||||||||||||
Consent Type Without Information | ||||||||||||||||||
Discussion On June 13, 2017, the School Board approved the Guaranteed Maximum Price (GMP) submitted by Wharton-Smith, for the District School Security #2 Project in an amount not to exceed $5,826,805.00. Change orders were subsequently approved, increasing the contract sum to $5,922,662.28. The work has been completed and audited. The final project cost is $5,654,311.34 which includes $4,800,644.74 contracted costs and $853,666.60 owner direct purchases. The unused balance is $268,350.94 Because the cost of construction is over $300,000 the Florida Department of Education requires the Superintendent to sign the Certificate of Final Inspection (OEF-209) following certification by Engineer/Architect of Record and the Building Official. | ||||||||||||||||||
Recommendation Authorize the Superintendent to sign FDOE OEF Form 209 - Certificate of Final Inspection for the project. | ||||||||||||||||||
Authority for Action F.S. 1001.42 | ||||||||||||||||||
Involves Expenditure of Funds Directly in the Classroom No | ||||||||||||||||||
Source of Funding Agenda Item will not Require the Expenditure of Funds |
||||||||||||||||||
Financial Impact
| ||||||||||||||||||
Legal Counsel Review No |
||||||||||||||||||
Contact Susan Hann, P.E., Assistant Superintendent Facility Services 633-1000 ext 11446 | ||||||||||||||||||