Rockledge High School - Design Build Services
Meeting Date(s)
Consent w/o Information - 06/30/2020
Consent Type
Without Information
Discussion

The locker room air conditioning project at Rockledge High School is included in the FY 20-21 capital plan. The project was previously designed as part of the Rockledge High School facility renewal project and is ready for construction. As this has been a longstanding need at the school, Facilities Services is proceeding with the project. 

Wharton Smith, Inc. (Wharton) has submitted a Guaranteed Maximum Price (GMP) in an amount not to exceed $209,150 under their continuing contract for construction management services. Administration and permitting costs are estimated at $8,000.

Board approval is required for purchase orders over $50,000. The standard agreement template has been used, which does not require legal review.

 

 

Recommendation

Approve the total project construction budget in the amount of $217,150 for the locker room air conditioning project at Rockledge High School.

Approve the Guaranteed Maximum Price submitted by Wharton in an amount not to exceed $209,150 under their continuing contract for design build services for the locker room air conditioning project at Rockledge High School.

Authority for Action
Involves Expenditure of Funds Directly in the Classroom
No
Source of Funding

Capital Projects
Financial Impact
FY Amount Budgeted Fund Cost Center Project Function Object Program

20/21

20/21

$209,150

$8,000

Yes

Yes

TBD

TBD

1011

1011

TBD

TBD

7400

7400

681

686

000

000

Legal Counsel Review
No
Contact
Susan Hann, P.E., Assistant Superintendent Facilities Services 633-1000 ext. 11446 David Lindemann, AICP, Director Planning and Project Management 633-1000 ext. 11463
Attachments
Rockledge Locker Room GMP Attachments.pdf