June 28, 2022 School Board Meeting
Title
District Wide Security - Design Build Services - SALES SURTAX RENEWAL
Meeting Date(s)
Consent w/o Information - 06/28/2022
Consent Type
Without Information
Discussion

The next phase of the Group A security projects is in process based on the Security Assessments and operational review by District Security. 

Wharton Smith, Inc. has submitted a Guaranteed Maximum Price in an amount not to exceed $237,545 for the next phase of the Group A projects under their continuing contract for design build services based on a Design Criteria Package previously developed by District staff for security projects. Administration and permitting costs are estimated at $10,000. Equipment is procured separately by the District and estimated to cost approximately $200,000.

The project will be funded through 2020 sales surtax. 

Board approval is required for purchase orders over $50,000. The standard form of the agreement has been used which does not require legal review. 

Recommendation

Approve the total project construction budget in the amount of $247,545 for the next phase of the Group A security project. 

Approve the Guaranteed Maximum Price submitted by Wharton Smith, Inc in an amount not to exceed $237,545 under their continuing contract for design build services for the next phase of the Group A security project. 

Authority for Action
F.S. 1001.42
Involves Expenditure of Funds Directly in the Classroom
No
Source of Funding

Sales Surtax
Financial Impact
FY Amount Budgeted Fund Cost Center Project Function Object Program
21/22 $237,545 Yes 397 Varies 600203 7400 681 000
21/22 $10,000 Yes 397 Varies 600203 7400 684/686 000
Legal Counsel Review
No
Contact
Susan Hann, P.E., Assistant Superintendent Facilities Services 633-1000 ext. 11446 David Lindemann, AICP, Director Planning and Project Management 633-1000 ext. 11463