South Alternative Learning Center - Construction Management Services - SALES SURTAX AND SALES SURTAX RENEWAL
Meeting Date(s)
Consent w/o Information - 06/28/2022
Consent Type
Without Information
Discussion

Intercom renewal projects are planned District-wide as part of the 2020 sales surtax renewal program. The project at South Alternative Learning Center has been designed by TLC  Engineering Solutions under their continuing contract for mechanical, electrical, plumbing and fire protection engineering services.

Heard Construction, Inc. has submitted a Guaranteed Maximum Price in an amount not to exceed $93,183.69 for the intercom renewal project at South Alternative Learning Center under their continuing contract for construction management services. This project is combined with intercom renewal projects at other sites to achieve economy of scale and reduce the construction management fee. Administration and permitting costs are estimated at $5,000.

This project is funded through 2020 sales surtax and 2014 sales surtax revenue over the $198 million target. The Independent Citizens Oversight Committee (ICOC) will consider allocating an additional pool of funds from the 2014 sales surtax revenue over the $198 million program target for intercom projects at its June 15, 2022 meeting. Capital is also available to partially fund this project.

Board approval is required for purchase orders over $50,000. The standard form of the agreement has been used which does not require legal review. 

 

Recommendation

Approve the total project construction budget for the intercom renewal project at South Alternative Learning Center in the amount of $98,183.69. 

Approve the Guaranteed Maximum Price submitted by Heard Construction, Inc. in an amount not to exceed $93,183.69 for the intercom renewal project at South Alternative Learning Center under their continuing contract for construction management services.

Approve the allocation of up to $50,000 from the 2014 sales surtax program over the $198 million program target for the intercom project at South Alternative Learning Center pending ICOC review.

 

Authority for Action
F.S. 1001.42
Involves Expenditure of Funds Directly in the Classroom
No
Source of Funding

Sales Surtax
Financial Impact
FY Amount Budgeted Fund Cost Center Project Function Object Program
21-22

$48,185.01

Yes 397

1018

600500 7400 681/687 000
21-22 $44,998.68 Yes 398 1018 541400 7400 681/687 000
21-22 $5,000.00 Yes 398 1018 541400 7400 686 000