Astronaut High School - Additional Construction Management Services
Meeting Date(s)
Consent w/o Information - 06/16/2020
Consent Type
Without Information
Discussion

At their January 28, 2020 meeting, the Board approved the Guaranteed Maximum Price (GMP) in an amount not to exceed $1,552,788.47 submitted by Core Construction Services of Florida, LLC (Core) for the sales surtax facility renewal project at Astronaut High School under their continuing contract for construction management services.

During construction it was discovered that 11 structural support steel column members were in an advanced state of deterioration. Core has submitted an owner-directed change order to repair and refurbish the columns in the amount of $123,696.18

The project will be funded through capital. This is not a sales surtax eligible expenditure.

Board approval is required for change orders over $50,000 or over 10%. The standard change order template has been used, which does not require legal review.

 

 

Recommendation

Approve Change Order #1 submitted by Core in the amount of $123,696.18 for the structural column repair and refurbishment at Astronaut High School.

 

Authority for Action
F.S. 1001.42
Involves Expenditure of Funds Directly in the Classroom
No
Source of Funding

Capital Projects
Financial Impact

 

FY Amount Budgeted Fund Cost Center Project Function Object Program

19/20

$123,696.18

Yes

370

0161

305963

7400

681

000

 

Legal Counsel Review
No
Contact
Susan Hann, P.E., Assistant Superintendent Facilities Services 633-1000 ext. 11446 David Lindemann, AICP, Director Planning and Project Management 633-1000 ext. 11463