Eau Gallie High School Building 25 Restrooms Renovation - Close Out
Meeting Date(s)
Consent Type
Without Information
Discussion

On March 8, 2022, the School Board approved the Guaranteed Maximum Price (GMP) submitted by Heard Construction, Inc., for the Eau Gallie High School Building 25 Restroom Renovation project in an amount not to exceed $551,456.43. Subsequently, a change order was approved increasing the amount to $576,854.17.

The work has been completed. The final project cost is $549,970.82 which includes $487,931.13 contracted costs and $62,039.69 in owner direct purchases. The unused balance is $26,883.35.

Because the cost of construction is over $300,000 the Florida Department of Education requires the Superintendent to sign the Certificate of Final Inspection (OEF-209) following certification by Engineer/Architect of Record and the Building Official.

Recommendation

Authorize the Superintendent to sign FDOE OEF Form 209 - Certificate of Final Inspection for the project.

Authority for Action
F.S. 1001.42
Involves Expenditure of Funds Directly in the Classroom
No
Source of Funding

Agenda Item will not Require the Expenditure of Funds
Financial Impact
FY Amount Budgeted Fund Cost Center Project Function Object Program
                 
Legal Counsel Review
No
Contact
Susan Hann, P.E., Assistant Superintendent of Facility Services 633-1000 ext. 11446
Attachments
OEF-209 version 2012 -TSARK -EGHS Bldg. 25.pdf
Agenda Plus