January 18, 2022 School Board Meeting | ||||||||||||||||||
Title Astronaut High School - Award of Bid | ||||||||||||||||||
Meeting Date(s) Consent w/o Information - 01/18/2022 |
||||||||||||||||||
Consent Type Without Information | ||||||||||||||||||
Discussion The Career & Technical Education (CTE) program requested an upgrade to the electrical system serving the welding lab to support more advanced equipment. Cape Design Engineering Co. prepared the design under their continuing contract for mechanical, electrical, plumbing and fire protection engineering services. Three bids were received for the electrical system upgrade from the District's continuing electrical contractors. The lowest bid was received from Lowe Electric, LLC in the amount of $142,251.32. Administration and permitting costs are estimated at $5,000. The project will be funded through capital. Board approval is required for purchase orders over $50,000. The standard agreement template has been used, which does not require legal review.
| ||||||||||||||||||
Recommendation Approve the total project construction budget in the amount of $147,251.35 for the electrical upgrade serving the Astronaut High School welding lab. Award the bid to Lowe Electric, LLC in the amount of $142,251.35 for the electrical upgrade serving the Astronaut High School welding lab.
| ||||||||||||||||||
Authority for Action F.S. 1001.42 | ||||||||||||||||||
Involves Expenditure of Funds Directly in the Classroom No | ||||||||||||||||||
Source of Funding Capital Projects |
||||||||||||||||||
Financial Impact
| ||||||||||||||||||
Legal Counsel Review No |
||||||||||||||||||
Contact Susan Hann, P.E., Assistant Superintendent Facilities Services 633-1000 ext. 11446 Jim Ross, Director of Maintenance 633-3580 ext. 13580 | ||||||||||||||||||
Attachments Bid Tabulation with Bids - Astronaut Welding Lab.pdf |
||||||||||||||||||
![]() |