Title
Imperial Estates Elementary School - Facility Renewal - Construction Management Services - SALES SURTAX
Meeting Date(s)
Consent w/o Information - 01/14/2020
Consent Type
Without Information
Discussion

The sales surtax facility renewal project at Imperial Estates Elementary School is scheduled for summer 2020. 

Wharton Smith, Inc. has submitted a Guaranteed Maximum Price (GMP) in an amount not to exceed $1,195,078 under their continuing contract for construction management services. The design was prepared by Above Group, Inc. under their continuing contract for mechanical, electrical, plumbing and fire protection (MEP) engineering services. Administration and permitting costs are estimated at $10,000.

The scope of the project is primarily HVAC renewal, controls, electrical and plumbing. Funding will be allocated by sales surtax categories based on the allocation distribution in Exhibit B attached. A separate chiller renewal is proposed which will either be done directly through Trane or through the construction manager as a change order. The estimated cost is $95,000. This amount is included in the finanacial summary for the project, but is not currenlty included in the contract.

The supplemental sales surtax funding ($520,000) for this project will be considered by the Independent Citizens Oversight Committee prior to the School Board's January 14, 2020 meeting.

Board approval is required for purchase orders over $50,000.

 

Recommendation

Approve the total project construction budget in the amount of $1,205,078 for the facility renewal project at Imperial Estates Elementary.

Approve the Guaranteed Maximum Price submitted by Wharton Smith, Inc. in an amount not to exceed $1,195,078 under their continuing contract for construction management services for the facility renewal project at Imperial Estates Elementary.

Approve the allocation of $520,000 in sales surtax revenue over $198 million for the project.

Authority for Action
F.S. 1001.42
Involves Expenditure of Funds Directly in the Classroom
No
Source of Funding

Sales Surtax
Financial Impact

 

FY Amount Budgeted Fund Cost Center Project Function Object Program

19/20

19/20

19/20

$1,175,681

$19,397

$10,000.00

Yes

Yes

Yes

398

398

398

0151

0151

0151

500000

650300

500000

7400

7400

7400

681/687

681

686

000

000

000

 

Legal Counsel Review
No
Contact
Susan Hann, P.E., Assistant Superintendent Facilities Services 633-1000 ext. 11446 David Lindemann, AICP, Director Planning and Project Management 633-1000 ext. 11463