Title Riverview - Facility Renewal - Construction Management Services - SALES SURTAX | ||||||||||||||||||
Meeting Date(s) Consent w/o Information - 01/14/2020 |
||||||||||||||||||
Consent Type Without Information | ||||||||||||||||||
Discussion The sales surtax facility renewal project at Riverview is scheduled for summer 2020. Heard Construction, Inc. has submitted a Guaranteed Maximum Price (GMP) in an amount not to exceed $475,638.69 under their continuing contract for construction management services. The design was prepared by Construction Engineering Group under their continuing contract for mechanical, electrical, plumbing and fire protection (MEP) engineering services. Administration and permitting costs are estimated at $8,000. The scope of the project is primarily HVAC renewal. Board approval is required for purchase orders over $50,000.
| ||||||||||||||||||
Recommendation Approve the total project construction budget in the amount of $483,638.69 for the facility renewal project at Riverview. Approve the Guaranteed Maximum Price submitted by Heard Construction, Inc. in an amount not to exceed $475,638.69 under their continuing contract for construction management services for the facility renewal project at Riverview. | ||||||||||||||||||
Authority for Action F.S. 1001.42 | ||||||||||||||||||
Involves Expenditure of Funds Directly in the Classroom No | ||||||||||||||||||
Source of Funding Sales Surtax |
||||||||||||||||||
Financial Impact
| ||||||||||||||||||
Legal Counsel Review No |
||||||||||||||||||
Contact Susan Hann, P.E., Assistant Superintendent Facilities Services 633-1000 ext. 11446 David Lindemann, AICP, Director Planning and Project Management 633-1000 ext. 11463 | ||||||||||||||||||
Attachments Riverview GMP Attachments.pdf Riverview CBA Form.pdf |
||||||||||||||||||
![]() |