Coquina Elementary School Facility Renewal
Meeting Date(s)
Consent Type
Without Information
Discussion

On March 27, 2018, The School Board approved the Guaranteed Maximum Price (GMP) submitted by Heard Construction, Inc., for facility renewal project at Coquina Elementary School in the amount not to exceed $1,958,208.63.  One change order for $43,254.60 was approved, increasing the contract sum to $2,001,463.23.

The work has been completed and audited.  The final project cost is $1,998,868.81.  The unused balance is $2,594.42.

Because the cost of construction is over $300,000 the Florida Department of Education requires the Superintendent to sign the Certificate of Final Inspection (OEF-209) following the certification by Engineer/Architect of Record and the Building Official.

Recommendation

Authorize the Superintendent to sign FDOE OEF Form 209 - Certificate of Final Inspection for the project.

Authority for Action
F.S. 1001.42
Involves Expenditure of Funds Directly in the Classroom
No
Source of Funding

Agenda Item will not Require the Expenditure of Funds
Financial Impact
FY Amount Budgeted Fund Cost Center Project Function Object Program
                 
Legal Counsel Review
No
Contact
Susan Hann, P.E., Assistant Superintendent of Facility Services 633-1000 ext 11446