Mims Elementary School - Additional Construction Management Services
Meeting Date(s)
Consent w/o Information - 08/22/2023
Consent Type
Without Information
Discussion

The Board approved a construction management contract in February 2023 with Wharton Smith, Inc. for the intercom renewal project at Mims Elementary School under their continuing contract for construction management services. At staff's request, Wharton Smith, Inc. submitted owner-directed change order #1 for security-related front office renovations in an amount not to exceed $53,460.31 with no time extension.

Administration and permitting costs have been previously budgeted. The project will be funded through remaining 2014 sales surtax.

Board approval is required for change orders over $50,000 or exceeding 10% oof the contract value. The standard form of the agreement has been used which does not require legal review. 

 

Recommendation

Approve the owner-directed change order #1 submitted by Wharton, Smith, Inc. in the total amount not to exceed $53,460.31 for the front office renovations at Mims Elementary School.

Authority for Action
F.S. 1001.42
Involves Expenditure of Funds Directly in the Classroom
No
Source of Funding

Sales Surtax
Financial Impact
FY Amount Budgeted Fund Cost Center Project Function Object Program
23/24 $53,460.31 Yes 398 0101 600200 7400 681 000
Legal Counsel Review
No
Contact
Susan Hann, P.E., Assistant Superintendent Facilities Services 321 633 1000 ext. 11446 David Lindemann, AICP, Director Planning and Project Management 321 633 1000 ext. 11463