Previous Item Print Next Item

April 27, 2021 School Board Meeting
Title
Creel Elementary School - Design Build Services - SALES SURTAX
Meeting Date(s)
Consent w/o Information - 04/27/2021
Consent Type
Without Information
Discussion

When the sales surtax renewal plan was presented, the Board inquired about adding the renovation of open classrooms. This concept was discussed with the Independent Citizens Oversight Committee at its August 19, 2020 meeting and added to the program at an estimated cost of $2 million for three schools.

Wharton Smith, Inc. has submitted a Guaranteed Maximum Price (GMP) in an amount not to exceed $1,190,631 under their continuing contract for design build services for the renovation of the open classrooms at Creel Elementary School . The proposal is based on a Design Criteria Package (DCP) prepared by TLC Engineering Solutions under their continuing contract for mechanical, electrical, plumbing and fire protection engineering services. The scope of work also includes new flooring and classroom LED lighting Building 1 which are elements of the year 1 2020 surtax renewal plan.  Administration and permitting costs are estimated at $15,000. The project will be funded through 2020 sales surtax renewal as follows:

Creel Classroom Renovation Project Funding Plan - Sales Surtax Renewal Plan
   
 Flooring - Building 1    $                      240,630
 Classroom LED Lighting    $                      157,169
 Reallocation from Media Center Cabinets and Furniture *   $                      200,000
 Supplemental Surtax Renewal Funds   $                      607,832
   
   $                  1,205,631
*Project was partially completed with other funding sources  

Although early in the sales surtax renewal program, sufficient revenue is expected to be able to fund the project. The project can also be partially funded through capital. The funding plan will be reviewed with the Independent Citizens Oversight Committee (ICOC) at its April 21, 2021 meeting.

Board approval is required for purchase orders over $50,000. The standard agreement template has been used, which does not require legal review.

 

 

Recommendation

Approve the total project construction budget in the amount of $1,205,631 for the renovation of the open classrooms at Creel Elementary School .

Approve the Guaranteed Maximum Price submitted by Wharton Smith, Inc. in an amount not to exceed $1,190,631 under their continuing contract for design build services for the renovation of the open classrooms at Creel Elementary School .

 

Authority for Action
F.S. 1001.42
Involves Expenditure of Funds Directly in the Classroom
No
Source of Funding

Sales Surtax
Financial Impact
FY Amount Budgeted Fund Cost Center Project Function Object Program
20/21 $1,190,631 Yes 397 6141 varies 7400 681/687 000
20/21 $15,000 Yes 397 6141 500000 7400 686 000
Legal Counsel Review
No
Contact
Susan Hann, P.E., Assistant Superintendent Facilities Services 633-1000 ext. 11446 David Lindemann, AICP, Director Planning and Project Management 633-1000 ext. 11463
Attachments
Creel Bldg 1 GMP Attachments.pdf
Agenda Plus